Mathematics
Medium
Question
Kamal will complete work in 20 days. If Suresh is 25% more efficient than Kamal, he can complete the work in________days.
A
14
B
16
✓ Official correct answer
C
15
D
11
Community credibility
Registered members can vote for the answer they believe is correct today and explain why. If the facts change after an election or news event, suggest a new option so others can vote it up.
A
14
No member explanations yet for this option.
B
16
No member explanations yet for this option.
C
15
No member explanations yet for this option.
D
11
No member explanations yet for this option.