Mathematics
Medium
Question
P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
A
10
B
8
C
18
✓ Official correct answer
D
19