HomeMathematicsP and Q can do a work in 30 days. Q and R can do...
Mathematics Medium
Question

P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?

A
10
B
8
C
18
✓ Official correct answer
D
19

Community credibility

Registered members can vote for the answer they believe is correct today and explain why. If the facts change after an election or news event, suggest a new option so others can vote it up.

A
10
Official option

No member explanations yet for this option.

B
8
Official option

No member explanations yet for this option.

C
18
Official option

No member explanations yet for this option.

D
19
Official option

No member explanations yet for this option.

Related Questions

Q
Probability of something in interest rate of XXX?
Medium · Mathematics
Q
80% of 700 = __________?
Medium · Mathematics
Q
P is 5 times as large as Q, the percent that Q is less than P is ____________?
Medium · Mathematics
Q
Who was Blaise Pascal?
Medium · Mathematics